Navigating Contractual Resilience: Force Majeure and Hardship Under UAE Law
Back to Blog
InsightsJuly 23, 2026Thajudheen Kinathiyil

Navigating Contractual Resilience: Force Majeure and Hardship Under UAE Law

Article Summary
  • •UAE law distinguishes between absolute impossibility, which terminates contracts under Article 273 (New Article 236), and 'exceptional circumstances' of severe hardship, which allows courts to rebalance obligations under Article 249 (New Article 224).
  • •To successfully invoke force majeure, you must satisfy four strict conditions: the event must be unforeseeable, external, unavoidable, and render performance objectively impossible rather than simply more expensive.
  • •Legal relief varies by jurisdiction; while UAE Mainland and DIFC imply statutory force majeure protections, ADGM courts typically require an express contractual clause, making precise, tailored drafting essential for all commercial agreements.

In the complex legal landscape of the United Arab Emirates, force majeure—or "superior force"—is a critical statutory doctrine that governs the excuse of non-performance when extraordinary, unforeseeable events disrupt contractual relationships. As a civil law jurisdiction, the UAE aligns with the tradition of codified legal systems found across France, Egypt, and other civil law countries, where force majeure operates as a statutory doctrine embedded in the civil code rather than a purely contractual mechanism. Like its French and Egyptian counterparts — from which the UAE Civil Code draws significant inspiration — UAE law applies force majeure principles independently of whether an express clause exists in an agreement, reflecting the civil law emphasis on legislative primacy and judicial intervention to maintain contractual equilibrium.

The UAE is currently entering a significant legislative transition; while the Civil Transactions Law (Federal Law No. 5 of 1985) is currently in effect, it will be repealed and replaced by the new Civil Transactions Law (Federal Decree-Law No. 25 of 2025) on June 1, 2026. Despite this modernization, the new framework largely preserves the established conceptual approach toward force majeure and exceptional circumstances.

The Dual Pillars of Relief: Article 273 and Article 249

The UAE Civil Code distinguishes between events that make performance impossible and those that merely make it burdensome:

  1. Impossibility of Performance (Article 273 / New Article 236): If a force majeure event renders a bilateral contract absolutely impossible to perform, the corresponding obligation ceases, and the contract is automatically terminated by operation of law. In cases of partial or temporary impossibility, only the affected portion of the contract is extinguished or suspended.
  2. Exceptional Circumstances and Hardship (Article 249 / New Article 224): This doctrine applies when an unforeseen public event makes performance excessively onerous or threatens a party with "grave loss" but does not reach the level of impossibility. In such instances, a judge or arbitrator has the discretionary power to rebalance the contract by reducing the oppressive obligation to a reasonable level. This is a mandatory provision that cannot be contracted out of by the parties.

Establishing a Valid Force Majeure Claim

To successfully invoke force majeure, UAE courts—which interpret the doctrine strictly—require the satisfaction of four cumulative conditions:

  • Unforeseeability: The event could not have been reasonably anticipated at the time of contracting.
  • Externality: The event must arise from circumstances entirely beyond the control of the party invoking the doctrine.
  • Unavoidability: The consequences could not have been mitigated despite reasonable efforts.
  • Absolute Impossibility: The event must render performance objectively impossible, rather than merely more expensive or commercially impractical.

Jurisdictional Nuances: Mainland vs. Free Zones

Parties must be aware of the specific legal system governing their contract, as the available relief varies significantly:

  • UAE Mainland: Relies on the statutory provisions of the Civil Code as described above.
  • DIFC: Article 82 of the DIFC Contract Law implies a statutory force majeure term into all contracts, even if they are silent on the matter.
  • ADGM: As an English common law jurisdiction, the ADGM recognizes force majeure only if an express clause is included in the contract; otherwise, parties must rely on the high threshold of the doctrine of "frustration".

Practical Applications and Recent Jurisprudence

Recent global and regional events have tested these legal frameworks:

  • COVID-19: While recognized as an extraordinary event, courts evaluated claims on a case-by-case basis. In a recent ADGM judgment [Abu Dhabi Court of Cassation (Commercial Appeal No. 1189/2021)] the court noted that while the pandemic was a significant "delay event," it did not automatically excuse non-performance if other factors contributed to the breach.
  • Regional Conflict: The Dubai Court of Cassation (Dubai Court of Cassation Commercial Case No. 1 of 2024) recently affirmed that the Russia-Ukraine war constituted a force majeure event, exempting a defendant from liability for failing to fulfil shipping obligations to Ukrainian ports.
  • Real Estate and Leases: Generally, force majeure does not excuse the payment of rent if the property remains available for occupation, as the payment obligation is treated as separate from the tenant's ability to operate their business.
  • Extreme Weather: The record storms of April 2024 are likely to trigger Article 249 (Hardship) rather than Force Majeure, as performance for most contracts became onerous but not permanently impossible.

Strategic Recommendations for Businesses

Parties seeking to mitigate risk should prioritize careful contractual drafting that specifically enumerates triggering events such as armed conflict, infrastructure damage, and government-imposed restrictions. Furthermore, compliance with procedural requirements is essential; most contracts require notification within 5 to 14 days of the triggering event. Failure to provide timely notice or demonstrate reasonable efforts to mitigate the impact of the disruption can prevent a party from successfully relying on force majeure protections. Additionally, where a contract forms part of a broader project, parties should ensure that force majeure provisions map “back-to-back” with related agreements — including supplier contracts, subcontracts, and lender agreements — to avoid gaps in protection across the contractual chain.

Equally important is a clear understanding of the remedies and consequences of invoking a force majeure clause. Parties should carefully review whether claiming force majeure entitles them to suspend obligations, terminate the contract outright, or merely extend applicable deadlines. Furthermore, the treatment of ongoing financial obligations during any suspension period — such as retainer payments, insurance premiums, and other recurring costs — should be expressly addressed in the contract to avoid disputes as to which party bears those costs while performance is excused.

Article authored by Mr. Thajudheen Kinathiyil, Junior Associate at QAF Legal.


Need Legal Guidance?